3.“The shortest total length of a project is determined by the longest path through the network.”Explain the concept behind this statement.Why does the longest path determine the shortest projectlength?This is based on the concept of critical path.The critical path combines the project activity network (the order to be followed forstart/completion of activities) and the estimated time duration of activities in the sequence (howlong each activity will take to complete) to determine the length of time required to completethe project.The longest path of sequential events is used to establish the project’s duration because theevents in the path must be performed one after another.Adding the duration times of activities in the critical path will result in the shortest project length(i.e., how long it will take to perform required serial activities).